产品概述
The rotating blades of the GT13E2 turbine — three stages in the gas generator and power turbine — are the most thermally and mechanically loaded parts of the machine, and they are usually the component that decides whether an outage finishes on schedule. Stage 1 blades see the full turbine inlet temperature (about 1,100°C) plus the centrifugal load of 3,000 rpm, while stages 2 and 3 carry progressively cooler but still severe duty as the gas expands and accelerates. When a blade cracks at the leading edge, erodes from particulate, or loses its TBC to spallation, the entire hot-gas-path inspection (HGPI) or C-level overhaul is at risk of slipping its schedule and extending a costly outage. ZURN Power supplies new and reconditioned GT13E2 blades for all three stages, manufactured to OEM airfoil geometry with full material traceability, and we repair blades returned from the field in our own workshop. This page covers specifications, materials, supply scope, and how our blades fit your maintenance program — complementary to our GT13E2 vane, GT13E2 burner, GT13E2 rotor, and GT13E2 compressor parts. For asset managers the blade is also the longest-lead new item in the machine, so holding even a single spare stage changes the economics of a forced outage extension.
规格与材料
GT13E2 stage 1 blades are typically directionally solidified (DS) or single-crystal (SX) nickel-based superalloys such as René 80 or CMSX-class alloys, chosen for creep and thermal-fatigue resistance; stages 2–3 may use equiaxed IN738LC or similar, balancing cost against the lower local temperature. Each blade carries internal cooling passages — convection plus impingement — feeding film-cooling holes along the leading and trailing edges and tip that we reproduce to original diameter, angle, and count. The gas-washed surface is coated with an MCrAlY bond coat and a YSZ thermal barrier coating (TBC) roughly 0.3–0.5 mm thick, with the TBC thickness mapped so the aerodynamic profile is preserved. We hold airfoil profiles, chord, and twist to OEM drawings, balance each blade to class, and issue EN 10204 3.1 material certificates with chemical analysis and grain-structure reporting for DS/SX parts. Root forms, shroud, and tip geometry are matched so the blade installs without platform grinding or field modification. We verify each blade on a coordinate-measuring machine against the nominal and limit drawings, and we record the as-measured twist and leading-edge thickness so a replacement matches the neighbor it sits beside in the rotor rather than merely fitting the drawing.
Supply / Service Scope:
We supply stage 1, 2, 3 GT13E2 turbine blades in both new-cast and reconditioned condition, with blade sets balanced as a complete rotor stage to minimize residual unbalance. Our services around blades include a TBC strip-and-recoat cycle for returned blades, braze and weld repair of cracks and tip restoration, cooling-hole cleaning and laser re-drilling, and reverse-engineered blades for obsolescent rows where no drawing survives. We also perform high-speed balancing of the assembled stage and dimensional verification against the rotor fit. Pair your blade order with GT13E2 nozzle guide vanes, SEV burners, and combustor liners from our other part pages, or send blades to our GT13E2 repair workshop for refurbishment between outages. Lifecycle management — we track fired hours per stage and advise on rotation and retirement so you replace on condition, not on guesswork, and so a planned HGPI is never surprised by an expired row.
Compatibility & Applications:
Our GT13E2 blades fit standard GT13E2-1, and MXL-upgraded units and are cross-referenced to GE heritage documentation, so a blade from any vintage resolves to a buildable item. They suit combined-cycle (KA13E2), simple-cycle peaking, and CHP duty across 50 Hz markets. Typical triggers for replacement are a scheduled HGPI or C-level overhaul, foreign-object damage (FOD) or rubbing from bearing wear, TBC spallation beyond acceptance limits, and creep-limited life expiry on the hottest rows. O&M teams, EPC contractors, and asset owners all source from our line, and the same blades back up GT13E2 data-center power programs where availability is contractual. In 50 Hz markets from the Gulf to North Asia the GT13E2 is common enough that a vane or blade from a sister unit can be cross-shipped at short notice, and our stock bridges that gap during a peak-demand window.
为什么选择 ZURN:
Our blades are made in-house through superalloy precision casting, HIP densification, 5-axis CNC, TBC coating, and NDT — no outsourced mystery stock with an unverifiable pedigree. That lets us guarantee chemistry, coating thickness, and balance class, and to reproduce a discontinued blade from a single sample when the OEM no longer offers it. With stocks via our Hong Kong hub serving the US, Europe, and Russia, we cut the lead time that usually forces a costly outage extension when a blade fails acceptance at the outage window. Because we also repair blades, a returned stage can be refurbished and recertified rather than scrapped, lowering lifecycle cost per fired hour. Because the same facility casts, coats, and balances, a new blade and a repaired neighbor leave the line to the same spec and the same balance class — no mixing of pedigrees within one rotor.
获取报价:
Send your blade drawing or part number and outage date to sales@zurnpower.com (China: hanson@zurnpower.com/download. If you are mid-outage and a blade has just failed acceptance, call rather than email; we triage outage-critical requests the same day and can dispatch a balanced stage from stock where one is held.
GT13E2 涡轮叶片技术参数
GT13E2 燃气轮机涡轮叶片是整个机组中承受温度最高、应力最大的热端部件。祝燃动力提供一级、二级和三级涡轮叶片的全系列备件,覆盖 Alstom GT13E2 原厂全部料号,并支持 SEV 环保型燃烧系统升级叶片的逆向制造。
| 参数 | 一级叶片 | 二级叶片 | 三级叶片 |
|---|---|---|---|
| 基体材料 | GTD-111 DS 定向凝固 | IN738LC 等轴精铸 | IN738LC 等轴精铸 |
| 涂层体系 | TBC(YSZ 陶瓷层 + MCrAlY 结合层) | 渗铝涂层 | 渗铝涂层 |
| 叶高(mm) | 约 120 | 约 135 | 约 150 |
| 弦长(mm) | 约 45 | 约 50 | 约 55 |
| 冷却方式 | 气膜冷却 + 内部对流 | 内部对流冷却 | 无冷却 |
| 制造标准 | ISO 9001 / AS9100D 航空质量体系 | ||
叶片材料与制造工艺
涡轮叶片的制造是燃气轮机备件中技术难度最高的环节。GT13E2 一级叶片工作温度超过 1100°C,必须采用定向凝固(DS)工艺的高温合金。祝燃动力的叶片制造流程包括:蜡模精密铸造 → 定向凝固热处理 → HIP 热等静压 → 五轴数控加工叶冠和缘板 → TBC 涂层涂覆 → 荧光渗透检测 → 尺寸三坐标测量。
TBC 热障涂层由两层组成:底层为 MCrAlY 结合层(厚度约 0.15mm),采用真空等离子喷涂(VPS)工艺;面层为氧化钇稳定氧化锆(YSZ)陶瓷层(厚度约 0.30mm),采用电子束物理气相沉积(EB-PVD)工艺。该涂层体系可降低基体温度约 150°C,显著延长叶片使用寿命。
常见叶片缺陷与评估标准
| 缺陷类型 | 允许极限 | 修复方案 |
|---|---|---|
| 叶尖磨损 | 径向间隙增大 ≤ 0.5mm | 激光堆焊修复 + 重新加工叶尖 |
| 前缘微裂纹 | 长度 ≤ 3mm,深度 ≤ 0.8mm | 打磨去除 + 局部 TBC 重涂 |
| TBC 涂层剥落 | 面积 ≤ 叶身 10% | 剥离旧涂层 + 重新喷涂 |
| 蠕变伸长 | 纵向伸长 ≤ 0.3% | 超出则报废更换 |
| 晶界氧化 | 深度 ≤ 0.2mm | 去除氧化层 + 热处理恢复 |
所有到厂叶片均需经荧光渗透检测(FPI)和射线检测(RT)确认无内部裂纹后方可进入修复流程。祝燃动力提供完整的叶片检测报告,包含每片叶片的检测照片、尺寸记录和寿命评估结论。
叶片备件交付与库存
祝燃动力在香港设有全球物流中心,常规叶片备件库存可 7-14 天交付。紧急需求可通过空运加急,最快 72 小时到达全球主要机场。对于大批量订单(一级叶片 20 片以上),制造周期约 12-16 周。所有叶片备件附带材料质保书(MTC)、检测报告和安装尺寸图。