Gas Turbine Technical Articles

Most unplanned outage overruns are not inspection failures. They are planning failures — an interval arrived before the long lead time parts did. Here is how experienced operators turn the MI, CI and HGPI cycles of GT13E2 fleets into a parts and budget timeline that holds.

24k–33k EOH
Baseline hot gas path inspection window on E-class frames
12–18 mo
Lead time to lock hot gas path parts before an outage
50–100+
Equivalent operating hours a single emergency trip can consume

Gas Turbine Technical Articles

Manufacturing-grade notes on the Alstom / ABB fleet we support — GT8C, GT8C2, GT9, GT11NM, GT11N1, GT11N2, GT11D4, GT11D5, GT13E2-V96, GT13E2 MXL, GT24 and GT25. Written for the engineers who specify and buy the parts.